    Resource Reports

    There are several reports available under the Role Center > Resource Reports.

    Resource List

    This report provides a list of Resources.

    Options:

    1. To filter the report for one Resource, click the No. field drop-down under Filter:Resource and select a Resource.
    2. Under Filter Totals by: Enter a Date range in the Date Filter enter a Date range to narrow report results by Date.
    3. Click desired print option to generate the report.

    Resource List report

    Resource List report

    Resource Statistics

    View unit and dollar Statistics by Resource.

    Resource Statistics Options

    Resource - Statistics Filter: Resource

    1. No. To filter the report for one Resource, click the No. field drop-down under Filter:Resource and select a Resource.
    2. Type: To filter the report for a specific Resource Type click the Type drop-down and select either Person or Machine. If no filter is selected the report will include both Types.
    3. Base Unit of Measure: To filter the report for a specific Base Unit of Measure click the Base Unit of Measure drop-down and select from the list.

    Filter Totals by

    1. Enter a Date range in the Date Filter to narrow report results by Date.
    2. Click desired print option to generate the report.

    Report Statistics - Options

    Report Statistics report

    Cost Breakdown

    Displays Costs by Resource.

    Cost Breakdown Options

    Cost Breakdown - Filter: Resource

    1. No. To filter the report for one Resource, click the No. field drop-down under Filter:Resource and select a Resource.
    2. Type: To filter the report for a specific Resource Type click the Type drop-down and select either Person or Machine. If no filter is selected the report will include both Types.

    Filter Totals by:

    1. Base Unit of Measure: To filter the report for a specific Base Unit of Measure click the Base Unit of Measure drop-down and select from the list.

    2. Enter a Date range in the Date Filter to narrow report results by Date.

    3. Click desired print option to generate the report.

    Resource - Cost Breakdown

    Resource Cost Breakdown

    Budget vs. Actual

    This report to shows a comparison of Project Budget vs. Actual Amounts.

    Budget vs. Actual Options

    Budget vs. Actual - Filter: Resource

    1. No. To filter the report for one Resource, click the No. field drop-down under Filter:Resource and select a Resource.

    Filter Totals by:

    1. Period Type: Select a Period Type (Date, Week, Month, Quarter, Year) from the drop-down list to narrow report results by Period Type.

    2. Period Start: (Required) Enter a Period Start date to narrow report results by Period Start.

    3. Click desired print option to generate the report.

    Budget vs Actual

    Budget vs Actual

    Remaining Capacity

    View Resource Capacity compared to Budgeted Units.

    Remaining Capacity Options

    Remaining Capacity - Filter: Resource

    No.: To filter the report for one Resource, click the No. field drop-down under Filter:Resource and select a Resource.

    Filter Totals by:

    Date Filter: Enter a date in the Date Filterfield to narrow report results by Date.

    1. Click desired print option to generate the report.

    Remaining Capacity report

    Remaining Capacity report

    Resource Capacity vs. Budget

    Run this report to show Resource capacity compared to Budgeted Units.

    Resource Capacity vs. Budget - Options

    Resource Capacity vs. Budget - Filter: Resource

    No.: To filter the report for one Resource, click the No. field drop-down under Filter:Resource and select a Resource.

    Filter Totals by:

    Date Filter: Enter a date in the Date Filterfield to narrow report results by Date.

    1. Click desired print option to generate the report.

    Resource Capacity vs Budget report

    Resource Capacity vs Budget report

    Resource Planning Matrix

    Provides Resource information for planning. Use the Matrix Options section to filter results displayed in the Resource Capacity Matrix section at the bottom. Use the navigation buttons in the ribbon (Previous Set, Next Set, Previous Column, Next Column) to scroll between Resource Capacity Periods.

    Resource Planning Matrix

    Timesheet Status Analysis

    This report is used to analyze time entry hours by Timesheet Status, presented in a Resource Matrix overview. The color and formatting of the text changes to help the user visualize certain conditions.

    Field Name Description
    View by Specifies by which period amounts are displayed. Options:
    - Day
    - Week
    - Month
    - Quarter
    - Year
    - Accounting Period
    View as The View as options offer the following filters of the data:
    View as Data Shown Data shown in () Color Visualization
    Hours Open on Timesheet-(Capacity) Hours on Timesheet with Status = Open, the hours have not been submitted. Capacity Open hours on Timesheet as % of capacity: green >= 100; black >= 80; red < 80.
    Hours Submitted Hours on Timesheet with Status = Waiting XX Approval – XX = PM, LM, or PE OR Status = Waiting Posting (in journal). - All hours shown in red.
    Hours Rejected Hours on Timesheet with Status = Rejected - All hours shown in red.
    Hours Approved-(Capacity) Hours on Timesheet with Status = Posted, usage has been created. Capacity Hours Approved as % of capacity: green >= 100; black >= 80; red < 80.
    Hours Total-Warning) Total Hours - Total hours as % of capacity: green >=100; black >=90; red <90
    Note

    Hours Total-(Warning) An Alert icon is shown if there are hours on a Timesheet that are not posted. Clicking on the quantity, which includes the Alert icon, displays the Timesheet lines that are not posted.

    Timesheet Analysis Alert

    Timesheet Analysis Alert

    Line Filters

    Use the Line Filters section to add additional filters to narrow displayed results.

    Field Name Description
    Resource Group No. Specifies which Resource Group lines are displayed.
    Line Manager Specifies which Line Manager lines are displayed.
    Global Dimension 1 Specifies by which Global Dimension data is shown. Global Dimensions are the Dimensions that you analyze most frequently. Two Global Dimensions, typically for the company's most important activities, are available on all cards, documents, reports, and lists.
    Global Dimension 2 Specifies by which Global Dimension data is shown. Global Dimensions are the Dimensions that you analyze most frequently. Two Global Dimensions, typically for the company's most important activities, are available on all cards, documents, reports, and lists.

    Entry Filters

    Field Name Description
    Project No. Specifies which Project No. lines will be displayed.
    Project Manager Specifies which Project Manager lines will be displayed.
    Person Responsible Specifies which Person Responsible lines will be displayed.
    Global Dimension 1 Specifies by which Global Dimension data is shown. Global Dimensions are the Dimensions that you analyze most frequently. Two Global Dimensions, typically for the company's most important activities, are available on all cards, documents, reports, and lists.
    Global Dimension 2 Specifies by which Global Dimension data is shown. Global Dimensions are the Dimensions that you analyze most frequently. Two Global Dimensions, typically for the company's most important activities, are available on all cards, documents, reports, and lists.

    Usage Analysis

    Use this report to analyze posted time entries, presented in a Resource Matrix where the color and formatting of the text changes to help the user visualize certain conditions. For example, to view total hours as a percentage of capacity, select Total Hours-Pct of Capacity), which will display in Red (italicized) or Green to indicate Customer Hours vs. Capacity. in the screenshot below, the 40 hours posted represents 25% of the Resource's total capacity for the month (160 hours), so it displays in red as 40(25%).

    Usage Analysis

    Field Name Description
    View by Specifies by which period amounts are displayed. Options:
    - Day
    - Week
    - Month
    - Quarter
    - Year
    - Accounting Period
    View as The View as options offer the following filters of data:
    - Day
    - Week
    - Month
    - Quarter
    - Year
    - Accounting Period
    View as Data Shown Data Shown in () Color Visualization
    Total Hours-(Pct. of Capacity) Displays the Total Timesheet Hours posted as % of capacity. Capacity Total Project hours on Timesheet as % of capacity: Green >= 100; Black >= 80; Red < 80.
    Customer Hours-(Pct. of Capacity) Displays the Timesheet Hours posted to Customer Projects. Capacity Customer Project hours on Timesheet as % of capacity: Green > >= 100; Black >= 80; Red < 80.
    Internal Hours Timesheet Hours posted to Internal Projects - All hours displayed in Green.
    Billable Hours-(Pct. of Capacity) Displays billable Project Hours on Timesheet as % of capacity Capacity Green >= 100; Black >= 80; Red < 80.
    Non-Billable Hours Displays non-billable Timesheet Hours (Chargeable = False) posted to a Project; Chargeable = False. All hours displayed in Green

    For Color Visualizations, the following colors/conditions apply:

    Condition Description
    Submitted Text will display in Green color when >= 100% Capacity. Text will display in Italicized Red color when Submitted Hours < 100% Capacity or no Capacity exists.
    Approved Specifies Approved Hours in % of Total Hours. The text will display in Green color when the Approved Hours >= 100% of Capacity. Text will display in Italicized Red when Approved Hours < 100% of Capacity, or no time is approved.

    In this first example, the Resource has 40 hours of Capacity entered for week 28-2024, and the View by field is set to Week. The report compares the Resource’s Capacity entries for Week 28 in the year 2024, with their Capacity Hours set up in their Timesheet Configuration, which is 40-5. This determines they are at 100% Capacity for that week, and the text for that week is displayed in Green, as 40(100%).

    Usage Analysis

    However, if the View by field is changed to Month, instead of Week, the same 40 hours now displays text in Red as 40/22%, which indicates that the Resource’s Capacity for the month is 182 hours and they have only booked 40 hours. The 40 hours entered versus 182 hours Capacity for the month = 22%. The entry now displays that this Resource is only at 22% of their Capacity for the month.

    Usage Analysis

    Tip

    Click the cell with the numbers to drill down and view the Project Ledger Entries comprising the Alert condition.

    Usage Analysis - Line Filters

    Use the Line Filters section to add additional filters to narrow displayed results.

    Field Name Description
    Resource Group No. Specifies which Resource Group lines are displayed.
    Line Manager Specifies which Line Manager lines are displayed.
    Global Dimension 1 Specifies by which Global Dimension data is shown. Global Dimensions are the Dimensions that you analyze most frequently. Two Global Dimensions, typically for the company's most important activities, are available on all cards, documents, reports, and lists.
    Global Dimension 2 Specifies by which Global Dimension data is shown. Global Dimensions are the Dimensions that you analyze most frequently. Two Global Dimensions, typically for the company's most important activities, are available on all cards, documents, reports, and lists.

    Usage Analysis - Entry Filters

    Field Name Description
    Project No. Specifies which Project No. lines will be displayed.
    Project Manager Specifies which Project Manager lines will be displayed.
    Person Responsible Specifies which Person Responsible lines will be displayed.
    Global Dimension 1 Specifies by which Global Dimension data is shown. Global Dimensions are the Dimensions that you analyze most frequently. Two Global Dimensions, typically for the company's most important activities, are available on all cards, documents, reports, and lists.
    Global Dimension 2 Specifies by which Global Dimension data is shown. Global Dimensions are the Dimensions that you analyze most frequently. Two Global Dimensions, typically for the company's most important activities, are available on all cards, documents, reports, and lists.

    Workload & Availability

    Analyze budget and planning entries with additional filters to limit the display, as an example, to Resource Group or Line Manager. View Resource Workload based on individual Outlook entries.|

    Workload and Availability Report

    Field Name Description
    View by Specifies by which period amounts are displayed. Options:
    - Day
    - Week
    - Month
    - Quarter
    - Year
    - Accounting Period
    View as The View as options specifies hours in actual budgets planned for the Resource. Workload specifies the budgeted hours (Type = Order) on the Resource, (Available Hours) specifies the Resource Capacity minus the Workload Hours. View as filters:
    - Day
    - Week
    - Month
    - Quarter
    - Year
    - Accounting Period
    View as Data Shown Data Shown in () Color Visualization
    Order Description Data Shown Colors
    Quote Description Data Shown Colors
    Order and Quote Description Data Shown Colors
    Calendar Description Data Shown Colors
    Workload (Available Hours) Description Data Shown Colors
    In This Article
    Back to top Generated by DocFX