Resources - Norm Working Hours
Norm Working Hours are used to define normal working hours for Resources. You can also use this page to define special working hours with a Start Date (for example, if someone is working reduced hours for a certain period of time)
To create new Norm Working Hours:
Navigate to the Role Center > Setup > Resource Setup > Norm Working Hours.
Field Name | Description |
---|---|
Code | Specifies a Code that will be used to identify Norm Time. Examples are 40-5 (40 hours in 5 working days) 40-4 (40 hours in 4 working days). |
Start Date | Specify the month, day, and year (m/d/yyyy) when this Code should begin. |
Start Time Monday | Specifies the Start Time for the Resource for Monday of the week. |
End Time Monday | Enter the End Time for the resource for Monday of the week. |
Start Time Tuesday | Enter the Start Time for the Resource for Tuesday of the week. |
End Time Tuesday | Specifies the End Time for the Resource for Tuesday of the week. |
Start Time Wednesday | Specifies the Start Time for the Resource for Wednesday of the week. |
End Time Wednesday | Specifies the End Time for the Resource for Wednesday of the week. |
Start Time Thursday | Specifies the Start Time for the Resource for Thursday of the week. |
End Time Thursday | Specifies the End Time for the Resource for Thursday of the week. |
Start Time Friday | Specifies the Start Time for the Resource for Friday of the week. |
End Time Friday | Specifies the End Time for the Resource for Friday of the week. |
Start Time Saturday | Specifies the Start Time for the Resource for Saturday of the week. |
End Time Saturday | Specifies the End Time for the Resource for Saturday of the week. |
Start Time Sunday | Specifies the Start Time for the Resource for Sunday of the week. |
End Time Sunday | Enter the End Time for the Resource for Sunday of the week. |